Inspection Requests


Please give us 24 hour notice for electric service, building footing, approach, and sidewalk inspections.

Inspections are made at the following points:

  • PRIOR TO THE POURING OF THE FOOTING OR APPROACH OR SIDEWALK (REQUESTED BY GENERAL CONTRACTOR)
  • ELECTRICAL, MECHANICAL, PLUMBING COVERS (REQUESTED BY THE SUB-CONTRACTOR) AND THEN THE BUILDING ROUGH (REQUESTED BY THE GENERAL CONTRACTOR) PRIOR TO COVERING OF THE STRUCTURE
  • ELECTRICAL, MECHANICAL, PLUMBING FINALS (REQUESTED BY THE SUB-CONTRACTOR) AND THEN THE BUILDING FINAL (REQUESTED BY THE GENERAL CONTRACTOR) PRIOR TO OCCUPANCY
Temporary electrical service inspections are permitted and inspected separately from the rest of the structure.


Gas meters can be installed prior to the completion of the project if:

  1. The plumber has submitted Gas Piping Affidavit.
  2. The heating or plumbing final has passed. Or a temporary heat inspection has passed.
Inspection requests can be made by phone (563-344-4074) or email (building@bettendorf.org).

When requesting, please provide the following information: name, company name, entry code (if applicable), and contact phone number.