Inspection Requests
Please give us 24 hour notice for electric service, building footing, approach, and sidewalk inspections.
Inspections are made at the following points:
- PRIOR TO THE POURING OF THE FOOTING OR APPROACH OR SIDEWALK (REQUESTED BY GENERAL CONTRACTOR)
- ELECTRICAL, MECHANICAL, PLUMBING COVERS (REQUESTED BY THE SUB-CONTRACTOR) AND THEN THE BUILDING ROUGH (REQUESTED BY THE GENERAL CONTRACTOR) PRIOR TO COVERING OF THE STRUCTURE
- ELECTRICAL, MECHANICAL, PLUMBING FINALS (REQUESTED BY THE SUB-CONTRACTOR) AND THEN THE BUILDING FINAL (REQUESTED BY THE GENERAL CONTRACTOR) PRIOR TO OCCUPANCY
Gas meters can be installed prior to the completion of the project if:
- The plumber has submitted Gas Piping Affidavit.
- The heating or plumbing final has passed. Or a temporary heat inspection has passed.
When requesting, please provide the following information: name, company name, entry code (if applicable), and contact phone number.