THE LANDING: A Premier Project - In The Works!
The Landing is a PREMIER PROJECT - Community Aquatic Facility & Ice Rink - NOW UNDER CONSTRUCTION through a PREMIER PARTNERSHIP between the City of Bettendorf and the YMCA of the Iowa Mississippi Valley. As you scroll down this page, you will find renderings of what The Landing will look like when it's finished, a timeline of the project, a live stream of the construction site, as well as important updates. We have also provided an overview of The Landing here.
Questions? You can email thelanding@bettendorf.org and we will answer them for you!
TASK
|
ESTIMATED TIME FRAME | PROGRESS STATUS | RESPONSIBILITY |
Approved Shared Use Agreement with YMCA & Professional Services Contract with RDG | October 2022 | Complete | City of Bettendorf/YMCA |
Schematic Design | October 2022 | Complete | RDG Design Team |
Design Development | November 2022 | Complete | RDG Design Team |
Construction Documents | January 2023-March 2023 | Complete | RDG Design Team |
Bidding Phase | April 2023 | Complete | City of Bettendorf/RDG Design Team |
Construction | May 2023-May 2024 | In Progress | General Constructors, Inc. |
LIVE STREAM of Construction Site at The Landing:
UPDATES
September 18, 2023 - 3 Months Into Construction
- Demolition is complete.
- Site work - including utility installation and parking lot construction - are well underway.
- The pool mechanical building and bath house foundations are complete, along with footings for the ice rink warming building.
- All four buildings, including the admissions building which will begin excavation next week, are expected to go vertical very soon.
- Floor sections of the zero-depth entry area of the main activity pool will also be poured this coming week.
July 25, 2023 - Demolition Nearly Complete
- Demolition of the existing facility is substantially complete.
- Site grading for the aquatic facility and building areas is also mostly complete.
- Excavation and shoring for the main activity pool has begun.
- Construction on the pool mechanical building is expected to begin on Wednesday, July 26.
June 1, 2023 - The Landing Awarded $790,000 Grant
The City of Bettendorf and the YMCA of the Iowa Mississippi Valley are excited to announce that The Landing has been awarded a $790,000 CAT (Community Action and Tourism) Grant from the Iowa Economic Development Authority thanks, in part, to The Landing Community Campaign which raised $14,712 from 97 donors between May 15th and June 1st, 2023.
May 26, 2023 - The Landing Groundbreaking Ceremony Announced
On Friday, June 2nd at 9am, the City is going to kick off its day-long 120th Birthday Community Celebration with a Groundbreaking Ceremony at The Landing.
The event will include remarks by Bettendorf Mayor Bob Gallagher, YMCA of the Iowa Mississippi Valley Board Chair Mo Hyder, RDG Planning & Design, and General Constructors, Inc. (GCI) – which was chosen by Bettendorf City Council in early May 2023 to construct a large component of this multi-million-dollar project.
WE NEED YOUR HELP! As part of our funding model, the YMCA of the Iowa Mississippi Valley and the City of Bettendorf have applied for the Iowa Economic Development Authority’s CAT (Community Action and Tourism) Grant.
On May 4, the Enhance Iowa Board heard our presentation and asked their staff for a recommendation. Their staff recommended a grant of $750,000, but in order to secure that money the board wanted to see more community participation in the fundraising.
This is why we need your help. We are asking for a contribution – big or small – to show your support for this PREMIER PROJECT and PARTNERSHIP: www.bettendorf.org/TheLandingCommunityCampaign
The City of Bettendorf is excited to announce that General Constructors, Inc. (GCI) of Bettendorf has been chosen out of three bidders to construct a large component of The Landing - a state-of-the-art aquatic facility - at the corner of 23rd Street and Middle Road.
On Tuesday, May 2, 2023, Bettendorf City Council unanimously approved a contract awarding GCI as the General Contractor of this $18 million construction project, which will occur in two phases to ensure the project can be successfully completed within the established budget while maintaining all the amenities that were presented to the community:
Phase 1: Large Activity Pool (Green on Graphic Below) & 4 Supporting Buildings
Construction Starts May 2023 - Completion Date May 2024
The 12,500-square-foot activity pool includes a zero-depth entry with spray feature, ninja-style ropes course, lap lanes, and a diving well with two diving boards and two climbing walls.
Phase 2: Slide Tower, Lazy River, Spray Pad (Blue on Graphic Below)
Construction Starts September 2024 - Completion Goal May 2025
The other amenities include a three-story-high slide tower with three slides, a 430-foot-long lazy river, and a 3,700-square-foot splash pad.
The Ice Side of The Landing
Following the completion of the aquatic facility, work will begin on the second component piece to The Landing - a permanent ice rink. This facility includes an outdoor ice rink that will be utilized in the winter with the ability to be converted to a turf field in the summer for community events like concerts, picnics, and movies - all of which will accentuate the fun and excitement taking place at the aquatic facility.
Several components of the ice rink are being constructed as part of the aquatic facility contract due to shared spaces and other construction efficiencies, bringing the total value of GCI's contract to $19.6 million. Work on the ice rink could be included in an amendment to Phase 2 of the aquatic facility, or it may be bid separately, depending on construction staging and pricing.
The Bettendorf City Council has approved a resolution approving the plans, specifications, and form of contract for The Landing. This means the project is now out for bid.
You can learn more about The Landing in Mayor Bob Gallagher's Message - released March 24, 2023:
March 7, 2023 - City Council Approves Next Step in Development Process of The Landing
The Bettendorf City Council has unanimously approved a resolution setting the date for a Public Hearing and directing the advertising of bids for The Landing. This is the first step of the approval process for a public improvement project. Several additional actions will be coming soon - including the consideration of a Site Development Plan by both the Planning & Zoning Commission and City Council, in addition to another Public Hearing on the plans and specifications, followed by a consideration to award the contract.
November 22, 2022 - Scott County Regional Authority Awards First Grant to The Landing
The Scott County Regional Authority (SCRA) held its Fall 2022 Awards Ceremony and distributed 52 grants to projects in our community - totaling $1,617,863.
One of those projects is The Landing, which received its first grant from the SCRA - totaling $166,667. The SCRA has a total commitment to The Landing of $4,000,000, which will equal 24 grants over 24 cycles (Fall and Spring).
October 4, 2022 - Bettendorf City Council Approves The Landing
The Bettendorf City Council has voted to move forward with three resolutions:
- A Shared Use Agreement with the YMCA of the Iowa Mississippi Valley to Create a City-Owned, YMCA-Operated Water Park
- The Sale of the Life Fitness Center to the YMCA of the Iowa Mississippi Valley to Transform into a Youth-Focused Recreational Center
- A Contract with RDG Planning & Design for Final Design of a State-of-the-Art Water Park and Permanent Ice Rink